Passivhaus Plus first for Shetland Isles
A Shetland self-build project has achieved Passivhaus Plus certification. It is one of only a handful of Passivhaus Plus schemes in the UK and the first in the Shetland Isles.
The Skeotaing project comprises a 4-bedroom house certified to the Passivhaus Plus standard, alongside a 2-bedroom Passivhaus Classic annex and double garage. The Passivhaus Plus standard was chosen to reduce future energy bills and address the climate emergency. The house is located on a north-facing slope with views to the north and west. The future addition of a wind turbine or more PV panels may change the rating of the annexe.
Key stats
|
![]() |
Construction
The house is built with timber frame, SIPs panels and a rendered concrete block exterior. The original design proposed highly insulated blockwork cavity walls to achieve high thermal capacity & retain heat in the winter. However, there was a shortage of block layers in the area. Timber-frame kits were then explored, already familiar to local builders.
The 235mm studs of a standard timber frame kit needed to be upgraded to a 245mm frame to accommodate the continuous layer of 50 mm of PIR wall insulation fixed to the inside of the kit.
The project's floor has 240 mm insulation plus a 100 mm thermo block insulation board around the perimeter under the walls and wall plate to minimise thermal bridging. High-performance triple-glazed doors and windows, with a bespoke non-standard spacer bar, have been complemented by Passivhaus-certified quintuple-glazed rooflights.
U-values |
![]() |
Floor: 0.074 W/m2K Ground floor concrete on PIR insulation boards |
Wall: 0.088 W/m2K Timber frame SIPS panels with rendered concrete blocks Wall build up exterior - interior:
|
Roof: 0.089 W/m2K Roof tiles on SIPS panels supported on Glulam ridge beam |
Building performance
Designed energy performance
Airtightness n50 (≤ 0.6ACH @ 50 Pa)
|
0.4 @ 50 Pa
|
Space Heating Demand (≤ 15 kWh/m².a)
|
13.55 kWh/m².a
|
Heating Load (≤ 10 W/m²)
|
8.65 W/m²
|
Primary Energy Renewable (PER) Demand (≤ 60 kWh/m².a*)
|
25 kWh/m².a
|
Primary Energy Renewable Generation
|
55 kWh/m².a
|
*+/-15 kWh/m².a allowance if offset by energy generation. See Passivhaus criteria.
Services
The services for the Passivhaus Plus project include solar PV, storage batteries, solar thermal, ground source heat pump, heat storage tanks, and two MVHR systems.
-
43 JA385W solar panels, each with individual solar edge optimiser
-
Roof-mounted solar thermal glass tubes for hot water
-
Electrical power storage via three 9.7kWA solar edge batteries
-
8kW ground source heat pump linked to five boreholes each 47 metres in depth
-
Two water tanks, one 500 litres for hot water plus one 200 litres for underfloor heating
Challenges
The site's orientation provided the biggest challenge to the project. It was clear that the low winter sun in Shetland would not permit much solar gain on the north side of a hill in Skeotaing. Larger windows were proposed to take advantage of the north/northwest views but had to be reduced in size to meet the PHPP energy balance requirements. South-facing windows to obtain much-needed winter solar gains were included but the design team found it difficult to get the heat balance to work. Extra insulation was added, and window performance was increased, by adding a higher-performance spacer bar and reducing glazing sizes. After 3 days of re-design, the PHPP model finally showed that the design could meet the Passivhaus Plus standard.
Drilling for the ground source heat pump also proved challenging, as the adjacent bog was not deep enough to accommodate the coils. The design was changed to drill into the granite rock below the site. However, the only available drilling rig in the Shetland Islands was used for dynamite at a quarry with a different drilling specification so the scheme was redesigned to work with a smaller pipe diameter and deeper holes.
The Passivhaus Plus standard was adopted to provide comfort, low energy bills and to prove that the Passivhaus Plus, energy positive standard, was possible even on a north facing slope at 60 degrees north in the Shetland Islands.
Allen Duncan, Allen Duncan Architects
Lessons learned
This was the first Passivhaus project for almost the whole design & construction team; goal-setting was vital. An early-stage training afternoon was held in a local sports centre for all site workers, joiners, electricians, plumbers, and the air pressure tester. It proved critical in getting the team to understand the importance of a continuous thermal envelope and airtightness.
It was instilled with all working on site that they were not building a normal project,but were, in fact, building a submarine where one tiny leak could sink the boat!
Allen Duncan, Allen Duncan Architects
Key team
|
You may also like
The projects below are all Passivhaus Plus certified. Take a look at our Plus & Premium page for further examples, and to get started on your Passivhus self-build journey, visit the Passivhaus goes Personal page.
![]() |
![]() |
![]() |
Further information
Skeotaing Shetland Passivhaus Plus
Passivhaus Powerhouses - Passivhaus Plus & Premium standards
STV News: Inspired by a flask, this house creates more energy than it needs - 6 October 2022
Scottish beacon: ‘We must build better’ architect says as he moves into new Passive House - 7 November 2023
Cameron and Ross, CASE, ScotFrame. |
14th February 2024
Get involved with the UK Passivhaus community
![]() |
![]() |
![]() |